The Smart Marty Sky Dispatch
How Overnight Work Shaped BWI’s Longest Runway
Crews rehabilitated Runway 10-28 using nightly work windows and coordinating with airport partners to avoid flight delays.
Crews at Baltimore/Washington International Thurgood Marshall Airport completed the rehabilitation of Runway 10-28, the airport’s longest runway and the one used by all large commercial air service.
Planning for the project began in 2024, with coordination among airport staff, engineers, construction managers, inspectors, contractors, air carriers, and air traffic control to fit construction around daily operations.
Two contractors worked in a joint venture to mill, repair cracks, apply a new seal, and lay fresh asphalt each night, with some shifts involving 40 to 50 truckloads of pavement and close coordination to minimize disruption.
Each night involved runway closures for milling, paving, asphalt compaction, cooling, and inspections, followed by reopening to air traffic by 6 a.m. the next morning, allowing daily flights to continue.
Airport leadership emphasized collaboration and planning, noting that nightly work maintained safety, efficiency, and capacity for ongoing air travel as the rehabilitation progressed.