US Navy orders three more E-130J Phoenix II nuclear communications aircraft
The US Navy has exercised a $1.13 billion contract option with Northrop Grumman for three more E-130J Phoenix…
The US Navy has exercised a $1.13 billion contract option with Northrop Grumman for three more E-130J Phoenix II test aircraft, bringing the number of aircraft under contract for the development of its future airborne nuclear communications platform to six.
According to the Pentagon’s contract announcement for November 25, 2026, the award covers the design, development and delivery of three system demonstration test aircraft, as well as an initial supply of spare parts. Work is expected to be completed by January 2030.
The US Navy has committed $4.18 million in fiscal 2027 research, development, test and evaluation funds at the time of the award. Most of the work will take place in Melbourne, Florida (35%), Marietta, Georgia (23%), and Richardson, Texas (15%).
US Navy doubles E-130J test fleet
The E-130J is based on the stretched C-130J-30 Super Hercules, fitted with Take Charge and Move Out (TACAMO) mission equipment, including a very low frequency (VLF) communications system from Collins Aerospace. Northrop Grumman leads the program, with Collins Aerospace and Lockheed Martin as subcontractors.
The US Navy’s initial $3.46 billion development contract, awarded in December 2024, covered three engineering development aircraft and included options for three additional test aircraft and up to six aircraft in an initial production batch.
The latest award exercises the options for the three additional test aircraft. In March 2026, the US Navy also awarded Northrop Grumman a $225.1 million contract modification for the E-130J’s training systems.
On October 15, 2026, Lockheed Martin delivered the first C-130J-30 airframe for the program to the US Navy at its Marietta facility. The aircraft is due to be handed over to Northrop Grumman for conversion.
E-130J faces mission equipment integration challenges
Fitting the nuclear communications equipment aboard the Super Hercules has proved more challenging than anticipated.
In its Weapon Systems Annual Assessment, published on July 2, 2026, the US Government Accountability Office (GAO) revealed that the program had pushed back its low-rate production decision by about a year.
The watchdog said that integration risks identified in an independent assessment in September 2024 “have morphed into realities.”
Contractors are now working to reduce the weight of existing mission systems so that they can be accommodated aboard the C-130J-30. The program office maintained that the E-130J was on track but, according to the GAO, provided no documentation to support that claim. The aircraft’s planned entry into operational service remains classified.
The E-130J will take over the TACAMO mission currently performed by the US Navy’s 16 Boeing E-6B Mercury aircraft. Its role is to ensure that US national leadership can maintain communications with the country’s nuclear-armed ballistic missile submarines, even in the event of a nuclear conflict. The US Navy named the aircraft Phoenix II in August 2025.